Tuesday, November 8, 2016

Bunker Update

     Bunker crew has been busy last couple of days working on some finish grading and cutting in some drain lines.  They had to quit at noon today because of the rain we got last night and today made it too muddy to work.  They are installing drain exits to get water out of bunker in case of rain.  They still have to come back and shape bottom and edges of bunkers and install drains lines and pea gravel in bottom of bunkers.  They have to get all edges and slopes around bunker to a slope we can mow.  This is Schaefer-Meyers 17th day on the job.

 # 10 bunkers has drain cut in and they covered rock bottom of the left bunker.
 
# 11 exit drain cut in to drain bunker.

Digging drain line to exit # 13 bunker

 Shaping # 14 bunker
#16 green side bunker exit drain line installed.
 
 