After Art's visit on Friday Schaefer-Meyer is busy making adjustments to bunkers and getting down to final shaping. They worked on holes 10, 14 and 16 yesterday. They will continue work on 10, 11 and 13 today. Art will be here on Thursday to make any adjustments or to approve Schaefer-Meyers work. Once approved drains and liner will be installed. Bunker sand is next followed by final grading and sodding. Hopefully rain stays away or we do not get a lot of rain on Wednesday so Schaefer-Meyer can continue work. Mother Nature has been kind to us Schaefer-Meyer has worked 13 out of 14 days so far. I hope they can keep going with minimum interruptions. Here are a few pictures of yesterdays progress.
#10 green
#14 green
# 16 green
No comments:
Post a Comment