Schaefer-Meyer has made some great progress on the bunker construction. Bunkers on 10, 11, 13, 14, and 16 all have drain lines installed and pea gravel covering them. The next step is to do some fine tune grading and install the bunker liner. We are getting real close to getting these holes completed. # 18 is almost ready to have drain lines cut in and they began to shape the right bunker on # 1. The way it is looking now they are planning on finishing 10, 11, 13, 14 and 16 and then start to work on the cart paths on holes 9 and 10 before it get too cold.
Gravel blanket in 10
Installing drain lines # 11