Construction update

     A lot has been happening the last couple of days.  Schaefer-Meyer has been busy taking out the cart paths on holes 9 and 10.  Drains have been installed on # 10 and we have started to pour the new path.  This path was in serious trouble we had voids under the path two feet deep in places.  On # 9 Schaefer-Meyer has installed new catch basins on the last half of the cart path and has began to trench in the drain lines on the first half.  # 9 also had some severe washouts under the path.  We are replacing 1200 feet of cart path between the two holes.  Here are some pictures of the progress.

This is void under # 9 path

Looking up toward green # 9 path. Notice the erosion in the middle

Grading # 9

This is the ditch cut under # 10 path

 Pouring the new path # 10

New path from bridge all the way to the forward tee # 10