Friday, December 23, 2016
Wednesday, December 21, 2016
Bunker update
Today Schaefer-Meyer was busy taking the old drains out of 2, 5, and 6 bunkers. Ground is still frozen. They can't do any shaping until frost is out of the ground. When you have frozen soil you cannot shape, the soil comes out in slabs. With 8 inch thick slabs you cannot fill or do any shaping. If you have a twitter account you can follow the construction progress there also. My twitter account is @ed_wachter I usually post where Schaefer-Meyer is working each morning.
Digging out old drainage in left bunker # 2
Wednesday, December 14, 2016
Bunker update
Holes 8, 10, 11, 13, 14, and most of 16 are done. Schaefer-Meyer sodded the rest of the back nine holes and the grass area of # 8 green. We still need a little sod on the fairway bunker on # 16 and more sod on # 17 rough. Bunkers look really good here are a few pictures of 8, 11, 13, and 14.
# 8 before sod
# 8 after sodding
# 11 sodded
# 11
# 13 looking from behind bunker
# 13
# 14
Saturday, December 10, 2016
# 10 bunker transformation
Here is some pictures of # 10 from pre - construction to finished product.
Shaping left bunker
New bunkers roughed in
Bunkers with liners installed
Sodding right bunker
View from approach
View from left rough
Friday, December 9, 2016
Bunker update
Sorry for the delay in updating my blog. Here what has happen in the past 2 weeks. All bunker liners have been installed. Bunker sand was installed on holes 10, 11, and 16. Drainage for 9 and 18 rough was installed. We have hole 10 completed and 16 almost done. Next week we will finish holes 11, 13, 14 and 16. Here are a few pictures.
Sodding right bunker #10
Raking left bunker #10
# 10 completed
Sodding Green side bunker #16
This machine rolls out sod
#16 green side bunker completed.
Wednesday, November 23, 2016
Happy Thanksgiving
On this day of Thanksgiving we pause and take a moment to be grateful for all our blessings: the freedom which this great country provides, the opportunity for growth and achievement, good health and the confidence and trust you have given to us. I can speak for my entire staff, everyone here truly loves and cares for Franklin County Country Club. Our best wishes for a Happy Thanksgiving.
Bunker update
Drainage and pea gravel has been installed in 10, 11, 13, 14, 16, bunkers. We have started to place liners into bunkers. We have 10 and 11 finished. Rain has stopped the liner installation. We will pick back up on Friday. Liners are important they keep subgrade from coming up into sand. Bunkers will be completely enclosed with liner. Sod line will come right down to 4 inch edge. Sod will say over part of the liner. This will keep our bunkers clean. Here are a few pictures of my staff installing liner. From a distance looks like we have white sand in our bunkers. Sorry for the illusion. I would have loved to use white sand but that would have added $50,000 to the cost of the project.
# 11 before liner
Installing liner
Finished
# 10 laying liner in right bunker
For every 1,120 sq. ft. roll of liner you need to nail 1000 6 inch staples to hold liner in place.
Right bunker # 10 completed
# 10 bunkers
Subscribe to:
Posts (Atom)





























