Sorry for the delay in updating my blog. Here what has happen in the past 2 weeks. All bunker liners have been installed. Bunker sand was installed on holes 10, 11, and 16. Drainage for 9 and 18 rough was installed. We have hole 10 completed and 16 almost done. Next week we will finish holes 11, 13, 14 and 16. Here are a few pictures.
Sodding right bunker #10
Raking left bunker #10
# 10 completed
Sodding Green side bunker #16
This machine rolls out sod
#16 green side bunker completed.