Tuesday, January 24, 2017

Cart Path # 10

     Schaefer-Meyer was back a work today after 4 weeks off due to bad weather.  They are working on  #10 cart path.  They removed the old cart path from the white tee to the bridge.  They will need a few more days for the path to dry down before they can do any grading.  They also have to install drain lines for the new path.  While cart path is gone we ask that you use the path on # 7 to access #10.  The gold and red tees are next to the path on the north side of the bridge.  You can still use the white, blue and black tees.  You can drive down path just past blue tees to get to the white tee.  You will have a short walk down hill to tee.  Sorry for any inconvenience.

 Removing path # 10
 This is how deep the void was under the path at forward tee. 
Cart path gone