Friday, July 15, 2016

Tee leveling update

     We finished the first phase of our tee leveling and sodding.  The red gold tee on 1, black tee on 3, white tee on 6 and the red gold tee on 14 have been completed.  It did rain before we could get all the sod laid on 6 and 14.  That was bad luck.  We need 1 more hour and we would have been done.  I would like to congratulate my  staff for job well done.  We did increase the size of all tee's. August 1st. we will do the remaining tee's,  1 white, 5 blue, and 12 white.  Here are few pictures of the Laser leveling and sodding. 

 Tilling up tee

Leveling Tee

Video of Laser leveling tee
 
 Putting finishing touches on level tee.
 
 We sodded tee's with 14 big rolls.
 
Tractor installs sod.  rolls are 3 1/2 feet wide
 
Video of sod installation
 
The rain caused a little bit of a problem.  We could not use tractor to install so we did it the old fashion way by hand.
#3 after sodded
 
After sod is laid we sand all seams.
 

No comments:

Post a Comment