13 and 14 cart path

We have finally fixed the bad cart path on holes 13 and 14.  It will be a much smoother ride now.  This job was a lot of work.  I had everyone on staff helping.  We mixed the concrete on site.  For every 94 lbs. bag of Portland cement we needed 22 scoops of sand, 33 scoops of 1 inch clean rock and about 8 gallons of water.  Some of the paths we had to haul concrete in wheel barrows.  We used a total of 45 bags of Portland cement.  My entire staff was exhausted when we finished. We still have to do some grading and sod work around the path.  Below are  a few pic's of the job
 #14 before
 Taking out old path
 Old path is gone
 Mixer
 Duane, Nick and Rob pouring concrete
 Nick and Rob finishing concrete
# 14 done
 
 
# 13 was a little easier.  We were able to use the bucket of the skid loader to haul the concrete.  No wheel barrows.  We could dump the entire mixer in the bucket.
 # 13 before
 Laying forms out
 Duane, Kyle, and Rob finishing
# 13 complete